@liaoning dalian specialized towerjet systems construction of a high-pressure mist spray system construction sequence 1. Pipeline opening: the main waterway switch is set at the starting point, the main waterway is set at 4 metres, three mains are required to connect the two ends of the water pipe, one of the spray tubes is inserted above, and a direct connection is installed at the top to connect the pipeline. (the distance between the spray tubes may be set as needed) the pipes are fixed by the clamps and screws. 2. Pump installation: first, the pumps will have to be attached to the racks by screws, while the rain sheds will be covered with the pumps and fixed with screws. Pumps will be tied to the pump with screw cards, following the living ribbon. The pump and the other end of the pipe will also need to be linked to the pipe by a live ribbon. 3. Smart controls have good waterproofing and can only be fixed to the fence. The inner line of the controller is fully connected to the power line, the remote control device line, the water level alert line and the pump power line. Controls are then connected to each other and can be put into operation. (b) composition; the encirclement shower system consists mainly of a ppr pipe, straight-through, three-way, bend-head, etc., which provides a spray water source, multi-stage pumps are given transmission power and smart controllers control the system. With a view to strengthening the concept of green development, the project will focus on the elements and objectives of integrated management of construction-related atmospheric pollution, with a view to strengthening regulation, and a solid effort will be made to improve the management of waste pollution at construction sites. Construction sites, coal fields, quarries, concrete mixing stations, landfills, waste treatment stations, etc., which exacerbate dust contamination, need to be covered with spray systems and water-smuggling dust. The spray system is a mandatory work site spray dust, concrete spray wetting, fire spray, garden spray, outdoor spray cooling, plant wetting cooling, etc. The composition of the system is that pm2. 5 is an important indicator of environmental monitoring, while air dusting is an important component of the pm2. 5 indicator and is targeted at all levels of the environmental sector. The plant spray details the material to be prepared according to the actual situation and layout of the project. 5. Project encirclement spray installation: construction of square cages, welding beams, panel installation. The installation is preceded by a clearer listing of intentions, which will allow the construction staff and developers to see clearly. The spray effect maps are installed on the frame, and the impact maps on the block spray are promotional effects maps. Some of the commercial building design performance maps do not meet the advocacy needs. 3. Construction block sprays for aesthetic treatment, painting of business names, safety, quality, civilized construction terms and commercial development projects, are strictly prohibited. 4. The installation of slogans above the project block shall be based on the scope, location, number, specification, content and duration of the promotional material approved by the municipal administration. 5. It is prohibited to use the project site to block out the outdoors. 6. The construction of the project block spray is complete, the plate is connected to the plate and the line is to be on a straight line; the plate and the plate must not leave a gap, i. E. The construction on the site cannot be seen outside the scene. 7. The installation of a red light along the project encirclement or the use of a safe reflector for night alerts to avoid unnecessary hazards to pedestrians or vehicles. In addition to the ability to separate the construction site from the road, the paint project block project, which has some impact on the project, plays a significant role in the marketing of products: 1. Dragon supermechanical control hosts can accept data collected by pm10 dust detectors and automatically turn on or off the dust-reduction system. At the same time, a remote-controlled operation control system could be activated and stopped to control the size of the fog and volume of water, thus allowing operators and tower-mounted drivers, ground concrete wet water maintenance and three functions of site fire protection. 2. A combination of site dust, concrete and wet water conservation at the site and fire protection at the site. 3. The system rotates using a tower of 360 to cover the site and air-to-ground stereojet, thus spreading airborne dust. In the event of a fire, the fire-fighting mode of the system can be activated immediately, the amount of water sprayed can be increased, the flames can be extinguished at high altitude and the fire quickly controlled。