Method of adjustment for price after change in construction

   2026-02-14 NetworkingName2040
Key Point:In 2019, when preparing for the first-level test for price engineers, the network prepared the content of the relevant knowledge points of the first-level test for price engineers, " analysis of the case of construction price " , for review, in the hope that it would help you to learn more quickly。First-rate engineer test case analysis free of charge testPrinciples for the treatment of project price change:The contractor should submit the

In 2019, when preparing for the first-level test for price engineers, the network prepared the content of the relevant knowledge points of the first-level test for price engineers, " analysis of the case of construction price " , for review, in the hope that it would help you to learn more quickly。

How do we change the unit price

First-rate engineer test case analysis free of charge test

Principles for the treatment of project price change:

The contractor should submit the work schedule and cost increases within 14 days of the change. In the event of a change of price in the construction process, the price adjustment method is as follows (2013 price regulation)

In the event that a change in work results in a change in the priced work list item or in the quantity of work performed, adjustments shall be made in accordance with the following provisions:

1) the list of priced works shall include the unit price applicable to the alteration project; however, an adjustment may be made when the change in work results in a change in the number of works on the list and the difference in the volume of work exceeds 15 per cent. When the volume of work is increased by more than 15 per cent, the combined unit price of the increased volume of work should be lowered; when the volume of work is reduced by more than 15 per cent, the combined unit price of the reduced volume of work for the remainder of the work should be increased。

2) where the list of priced works is not applicable but where there are items similar to the alteration works, reference may be made to the unit price of similar items to a reasonable extent。

3) where the list of priced works is not applied and is not similar to the change project, the unit price for the change project shall be proposed by the contractor on the basis of the change of project information, measurement rules and pricing methods, the information price issued by the project price management agency and the rate of fluctuations in the contractor's offer, and shall be subject to confirmation by the contractor。

Of which:

Float rate l = (1 — winning bid/bid control) x 100%

Non-tendered engineering contractor's quote floating rate l = (1 — value/construction chart budget) x 100%

4) where a change in the construction programme results from a change in the construction programme and changes in the project for the measure, the cost of construction for the general safety civilization may be adjusted to the cost of the actual change; the unit cost of the measure shall be adjusted to the principle of paragraph 1 above

(5) in the event that the consolidated unit price stated by the contractor in the volume list of works exceeds 15 per cent for the contractor's bid control price or the corresponding list of items in the construction chart budget, the combined unit price for the project change project may be adjusted by both parties in accordance with the following provisions:

1 p-0

Consolidated unit price for this category = p1x(1-l)x (1-15%)

2 > p1x (1+15%)

Consolidated unit price for this category = p1x (1+15%)

Of which:

P0 is the consolidated unit price stated by the contractor in the bill of quantities

P1 is the combined unit price for the bid control price or corresponding list of construction budget items

L is offering a floating rate for contractors

 